Phased Development Approach
____________________________________
|
Martin will be redeveloped
over a ten-year period. The redevelopment program will be sponsored
by the U.S. Army Corps of Engineers – Huntington District
and the Floyd County Fiscal Court. The Corps has established a four-phase
schedule for implementing the redevelopment program. The order of
the phases was determined ujointly with the project sponsor and
is further described in the project Real Estate Plan.
Phase 1
- Clearing/construction of the redevelopment site (6.4-acre hillside
location)
- Design and construction of key facilities (City Hall/Police
Station, Post Office, Martin Alternative School, Church, Mixed-Use
Commercial and Office Buildings, Public Space)
Phases 2 and 3
- Acquisition of downtown properties
- Clearing of existing downtown
- Fill and raise cleared site above floodplain (14 acres readied
for future development)
- Construct mixed-use redevelopment area
Phase 4
- Implement voluntary flood proofing program
- Apply nonstructural methods, including buy out and protection
in place
|
|
Photo Simulation:
Phased Development
|
|